Agricultural Verification | Building, Engineering | 3 | 2 | 5 Day Turnaround |
Airconditioning Change‐out | Building | 0 | 0 | Over the counter |
Commercial Addition | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
Commercial Miscellaneous | Building, (Zoning), Fire | 10 | 4 | 12 Day Turnaround |
Commercial Remodeling | Building, Fire | 10 | 5 | 12 Day Turnaround |
Demolition | Building, Zoning, (Engineering) (Fire) | 2 | 1 | 3 Day Turnaround |
Detached Accessory Unit | Building, Engineering, Zoning | 10 | 4 | 12 Day Turnaround |
Driveway | Building, Zoning, Engineering | 4 | 1 | 5 Day Turnaround |
Electric | Building | 4 | 1 | 5 Day Turnaround |
Fence/Wall | Building, Zoning, (Engineering) | 4 | 1 | 5 Day Turnaround |
Fire Suppression | Building, Fire | 4 | 1 | 5 Day Turnaround |
Foundation Only Permit (with Approval of Bo) | Building, Engineering, Zoning | 4 | 1 | 5 Day Turnaround |
Gas | Building | 4 | 1 | 5 Day Turnaround |
Grease Interceptor | Building, UTIL | 4 | 1 | 5 Day Turnaround |
Hood System | Building, Fire | 4 | 1 | 5 Day Turnaround |
Hurricane Shutters | Building | 4 | 1 | 5 Day Turnaround |
Irrigation System (1 Acre and Larger) | Building, Engineering | 4 | 1 | 5 Day Turnaround |
Landscaping | Building, Zoning, (Engineering) | 10 | 4 | 12 Day Turnaround |
Low Voltage | Building, (Fire) | 4 | 1 | 5 Day Turnaround |
Manure Bin | Building, Zoning, Engineering | 4 | 1 | 5 Day Turnaround |
Mechanical | Building (Fire) | 4 | 1 | 5 Day Turnaround |
Miscellaneous | Building (Zoning, Engineering) | 4 | 1 | 5 Day Turnaround |
Model Home ‐ Temporary | Building | 10 | 4 | 12 Day Turnaround |
Mold Remediation | Building | 4 | 1 | 5 Day Turnaround |
New Amusement, Social and Recreation | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Churches and Other Religious | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Hospitals and Institutions | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Hotels/Motels, Etc. | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Industrial | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Office/Bank Plaza | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Other, Non‐Residential | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Parking Garages | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Residential, 3 and 4 Family Buildings | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Residential, Attached | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Residential, Detached | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Residential, Multi‐Family | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Residential, Two-Family Buildings | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Schools and Educational | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Service Stations and Garages | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Stores and Customer Service | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
New Structures, Not Buildings | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
Plumbing/Backflow | Building, (Fire/UTIL) | 4 | 1 | 5 Day Turnaround |
Pool Barrier Permit | Building, Zoning (Engineering) | 4 | 1 | 5 Day Turnaround |
Refrigeration Permit | Building | 4 | 1 | 5 Day Turnaround |
Reroof | Building (Zoning) | 1 | 1 | 24 Hr Turnaround |
Residential Addition | Building, Zoning, Engineering | 10 | 4 | 12 Day Turnaround |
Residential Addition Over $25,000 | Building, Zoning, | 10 | 4 | 12 Day Turnaround |
Residential Addition, Garage, Carport, Storage | Building, Zoning, (Engineering) | 10 | 4 | 12 Day Turnaround |
Residential Remodeling | Building | 10 | 4 | 12 Day Turnaround |
Residential Remodeling Over $25,000 | Building | 10 | 4 | 12 Day Turnaround |
Roof Determination | Building | 4 | 1 | 5 Day Turnaround |
Screen Enclosure | Building, Zoning, (Engineering) | 4 | 1 | 5 Day Turnaround |
Sign | Building, Zoning | 4 | 1 | 5 Day Turnaround |
Solar Panel Installation | Building | 4 | 1 | 5 Day Turnaround |
Stable Non Residential | Building, Zoning, Fire, Engineering | 10 | 4 | 12 Day Turnaround |
Stable with Residence | Building, Engineering, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
Swimming Pool/Spa (Oakmont/Castellina) | Building, Zoning (UTIL) | 4 | 1 | 5 Day Turnaround |
Temporary Tent | Building, Zoning, Fire | 4 | 1 | 5 Day Turnaround |
Tenant Build‐out | Building, Zoning, Fire | 10 | 4 | 12 Day Turnaround |
Water Heater Change‐out | Building | 0 | 0 | Over the counter |